ACCA FM investment appraisal: the NPV pro forma and beyond

The biggest Section C question. Pro forma discipline wins the marks: years across the top, one line per cash flow, tax one column to the right.

By the Hamzah Academy faculty · Updated 26 November 2026
Enrol on WhatsAppACCA FM courseFree ACCA courses
INVESTMENT APPRAISALNPVthe pro formaIRRtwo-rate method%sensitivityEACspecial decisions
12marks for the NPV engine
T5the column students forget
4.2%price sensitivity in the example
2marks for the comment
NPV rulesRisk and uncertaintyExample: NPVExample: sensitivityFAQs

Investment appraisal is Area C of ACCA FM and usually the largest Section C question. The marks are spread across a pro forma, so one wrong line costs one or two marks, not the question, provided the layout is clear. This guide sets out the pro forma, the rules on inflation, tax and working capital, the risk techniques, and two worked examples from Hamzah’s revision notes with the examiner’s traps.

FM guide series:How to pass FMWorking capitalInvestment appraisalFinance and cost of capitalValuation and riskFM formulas

NPV: the pro forma, relevant cash flows, tax and inflation

The story
Ravi Co can buy a machine for $3m. Should it?
The machine makes a product that sells for $25 a unit, for four years. Prices will inflate, tax is paid a year late, and cash is needed for working capital. The board wants one number: does this project make the shareholders richer? That number is the NPV, and Section C asks you to build it.
The sales director says“We will sell 420,000 units. It is a great product.”
The finance director says“Show me the cash, year by year, after tax.”
Before you build: relevant or not?
Eight items from a typical question. Decide if each one goes into the NPV.
Market research already paid for
Contribution lost by using a scarce material
Depreciation on the new machine
Extra working capital needed at the start
Interest on the loan that funds the machine
Head-office rent shared out to the project
Extra fixed costs caused by the project
Tax on the extra profit
Build Ravi Co’s NPV, one working at a time
Try each working on paper first, then reveal it. Volumes are 100,000 / 120,000 / 110,000 / 90,000 units.
1
Step 1Find the nominal discount rateReal cost of capital 7%, general inflation 4%. Use Fisher.(1.07 × 1.04) − 1 = 11.28% → use 11%
2
W1Revenue$25 in current price terms, inflating at 4%. Year-n price = 25 × 1.04ⁿ = 26.00, 27.04, 28.12, 29.25. Multiply by the units.$000: 2,600 / 3,245 / 3,093 / 2,632
3
W2Variable cost$12 inflating at its own rate of 5%: 12.60, 13.23, 13.89, 14.59.$000: 1,260 / 1,588 / 1,528 / 1,313
4
W3Fixed cost$300,000 a year inflating at 3%.$000: 309 / 318 / 328 / 338
5
W4Capital allowances25% reducing balance: 750, 562, 422. Year 4 is a balancing allowance: 1,266 − 300 scrap = 966. Tax saved at 30%, received one year later.$000: 225 / 169 / 127 / 290 in T2 to T5
6
W5Working capitalThe requirement grows with inflation: 250, 260, 270, 281. Only the change each year is a cash flow, and the total comes back at the end.$000: T0 (250), T1 (10), T2 (10), T3 (11), T4 +281
NPV = +$272,000Net cash flows ($000), T0 to T5: (3,250), 1,021, 1,244, 994, 1,318, (5). Discounted at 11%.Now say what it means. The NPV is positive, so the project increases shareholder wealth and is financially acceptable, subject to the accuracy of the estimates.
Which technique does the question need?
Tap a situation.
Equivalent annual costEAC = PV of the costs of one cycle ÷ annuity factor for the cycle length. Choose the lowest EAC.
Profitability indexIf projects are divisible, rank by NPV ÷ initial investment. If indivisible, try combinations for the highest total NPV.
Lease vs buyDiscount at the post-tax cost of borrowing = pre-tax rate × (1 − T). Pick the lower PV of cost.
PaybackYears until cumulative cash flow reaches zero. Simple, with a liquidity focus, but it ignores later flows and the time value of money.
Trust NPVNPV shows the absolute increase in wealth. IRR is relative and can mislead on scale.
ROCE / ARRAverage accounting profit ÷ average investment, or ÷ initial investment. Say which. It uses profit, not cash.
Examiner trapThe Sep/Dec 2025 report lists these losses: inflating fixed costs at wrong rates; tax in the wrong year despite "one year in arrears"; forgetting the year-5 tax and CA line; no comment on acceptability. Also: WC is the change each year and is recovered at the end; scrap value is taxable via balancing allowance/charge.
The rules, for revision
Open a topic when you want the full list.
NPV pro forma (nominal, tax in arrears)
LineT0T1T2T3T4T5
Year012345
Sales revenue (inflated)XXXX
Variable costs (inflated)(X)(X)(X)(X)
Incremental fixed costs(X)(X)(X)(X)
Taxable cash flowXXXX
Tax @ T% (one year later)(X)(X)(X)(X)
CA tax benefit (one year later)XXXX
Investment / scrap(X)X
Working capital (incremental)(X)(X)(X)(X)X
Net cash flow(X)XXXX(X)
Discount factor @ nominal r1.000DFDFDFDFDF
PV → sum = NPV
Relevant cash flows
IncludeFuture, incremental, cash. Opportunity costs. Incremental fixed costs only. Tax effects. Working capital.
ExcludeSunk costs, depreciation, apportioned/absorbed overheads, interest (already in discount rate), non-incremental fixed costs.
Capital allowances

25% reducing balance (or straight-line if told). Tax saving = CA × T. Final year: balancing allowance = written-down value − disposal proceeds (balancing charge if proceeds > WDV — extra tax). If first CA is claimed at T0 (same-year), say so — the exam usually claims the first CA in year 1 with tax saved in year 1 or 2.

Inflation & real vs nominal
Fisher(1 + i) = (1 + r)(1 + h) i = nominal, r = real, h = general inflation
Nominal methodInflate each flow at its specific rate; discount at nominal rate. Default method when rates differ.
Real methodUninflated flows at real rate — only valid if all flows inflate at the general rate. Approximation: deflate nominal flows by (1+h)^n.
InflatingYear-n price = today's price × (1 + rate)^n — "current price terms" means inflate from year 1
Working capitalInflate the WC requirement at its own rate; the cash flow each year is the increase in the requirement; recover the total at the end
Other techniques
PaybackYears until cumulative cash flow ≥ 0. Simple, liquidity focus, ignores post-payback flows and time value. Discounted payback uses PVs.
ROCE / ARRAverage accounting profit ÷ Average investment [(initial + scrap)/2] — or ÷ initial investment. Say which. Uses profit not cash; ignores time value.
IRRL + [NPVL ÷ (NPVL − NPVH)] × (H − L). Accept if IRR > cost of capital. Problems: multiple IRRs, assumes reinvestment at IRR, conflicts with NPV for mutually exclusive projects — NPV is superior.
Why NPV is bestAbsolute wealth increase, uses cash, time value, all flows, correct decision rule; IRR is relative and can mislead on scale.
Special decisions
Lease vs buyDiscount at post-tax cost of borrowing = pre-tax rate × (1 − T). Buy: cost, CA benefits, scrap. Lease: rentals (usually in advance, T0…), tax relief on rentals one year later. Pick the lower PV of cost.
Asset replacement (EAC)EAC = PV of costs of one cycle ÷ annuity factor for cycle length. Choose the lowest EAC. Assumes constant technology/prices.
Capital rationingDivisible: rank by profitability index = NPV ÷ initial investment (or PV inflows ÷ outlay). Indivisible: trial combinations for max total NPV. Hard rationing = market; soft = internal.
Annuity / perpetuityAF = (1 − (1+r)^-n) ÷ r. Perpetuity = 1/r. Growing perpetuity = 1/(r − g). Delayed: multiply by DF of the year before it starts.

Real to nominal rate (Fisher)

Risk and uncertainty: sensitivity, ENPV and the discussion

The story
The NPV is +$272,000. But the price is a guess.
Ravi’s sales director admits the $25 selling price is an estimate. The board asks the obvious question: how wrong can it be before this project loses money? That is sensitivity analysis.
Try it: push the price down
The PV of Ravi’s post-tax revenue is $6,549,000. Slide the price down and watch the NPV.
Which estimate matters most?
The lowest percentage is the most sensitive variable. That is where management attention goes.
Selling price4.2%
Discount rate37%
A small competitive price cut removes the whole NPV. The cost of capital would have to rise from 11% to about 15% to do the same.
One decision that costs marks every sitting
Ravi’s IRR is 15.1% and its cost of capital is 11%. For the discount rate sensitivity, what do you divide the 4.1% by?
11%. (15.1% − 11%) ÷ 11% = 37%. Percentage changes are always from the original figure, so the base is the original discount rate, not the IRR.
Examiner trapMar/Jun 2025 & exam kit: candidates forgot the tax effect on the variable, ignored tax in arrears, and used undiscounted flows in the denominator. Percentage changes are always from the original figure.
Examiner trapWhen asked to "compare sensitivity and probability analysis", compare them — usefulness for decision-making, information needs, risk attitude — rather than writing everything you know about each separately.
The rules, for revision
Open a topic when you want the full list.
Sensitivity analysis
Sensitivity of a variableNPV ÷ PV of the cash flows relating to that variable (post-tax if tax applies) × 100%
Discount rate(IRR − cost of capital) ÷ cost of capital × 100% — base is the original discount rate, not the IRR
Sales volumeUse PV of contribution (not revenue) — volume changes affect variable costs too
InterpretationLowest % = most sensitive variable → management attention / further research

Limitations: one variable at a time; no probabilities; doesn't say what to do; assumes independence of variables; management may still accept a sensitive project.

Probability analysis / ENPV

ENPV = Σ (NPV × probability). With sequential years, build a joint probability table (multiply along each branch). Discount each branch's flows — probabilities do not remove discounting.

Probability of negative NPV = sum of the joint probabilities of branches with NPV < 0 — it is a %, not a $ amount, and it is not a sensitivity.

Most likely outcome = branch with the highest joint probability. ENPV is an average that may never occur; useful for repeated decisions; ignores risk attitude; probabilities are subjective.

Risk vs uncertainty & other methods
RiskOutcomes and probabilities can be estimated. Uncertainty: cannot — use payback, sensitivity, conservative estimates.
Risk-adjusted discount rateAdd a premium for riskier projects; project-specific rate via CAPM (see Area E). Adjusted payback, simulation (Monte Carlo — many variables, gives a distribution, complex), expected values.
Discussion one-liners that score

"The project has a positive NPV of $X, so it increases shareholder wealth and is financially acceptable — subject to the accuracy of the estimates, particularly [most sensitive variable]."

"Real options / strategic benefits not captured in the NPV should also be considered." (Keep to one sentence in FM.)

"Non-financial factors: environmental impact, employee and customer response, fit with strategy, availability of finance."

Section C write-up checklist

Years across the top, one line per flow, all workings labelled (W1 sales, W2 CA…)

Every table ends with NPV = $X → decision

Discussion parts: 2 marks per point → point + explanation + application

Do the calculation parts first if they are worth more; leave 8–10 min for the discussion

Worked example: NPV with inflation, tax in arrears and working capital

The Section C engine. Build the pro forma exactly like this.

Ravi Co

Question

Machine costs $3,000,000 now, scrap value $300,000 at the end of year 4 (in year-4 money).

Sales volume: 100,000 / 120,000 / 110,000 / 90,000 units in years 1–4. Selling price $25 per unit and variable cost $12 per unit, both in current price terms; price inflates at 4% p.a., variable cost at 5% p.a.

Incremental fixed costs $300,000 p.a. in current price terms, inflating at 3% p.a.

Working capital of $250,000 is needed at the start, rising each year with general inflation of 4%, and is recovered at the end of year 4.

Tax 30%, payable one year in arrears. Capital allowances 25% reducing balance, balancing allowance in the final year. Real cost of capital 7%, general inflation 4%.

Required: calculate the NPV and comment. (12 marks)

Answer

Step 1 – nominal discount rate(1.07 × 1.04) − 1 = 11.28% → use 11%.
W1 Revenue ($000)Year-n price = 25 × 1.04ⁿ → 26.00, 27.04, 28.12, 29.25 → × units = 2,600 / 3,245 / 3,093 / 2,632
W2 Variable cost12 × 1.05ⁿ = 12.60, 13.23, 13.89, 14.59 → × units = 1,260 / 1,588 / 1,528 / 1,313
W3 Fixed cost300 × 1.03ⁿ = 309 / 318 / 328 / 338
W4 Capital allowances ($000)Y1 3,000 × 25% = 750; Y2 562; Y3 422; WDV after Y3 = 1,266; Y4 balancing allowance = 1,266 − 300 = 966. Tax saved at 30% = 225 / 169 / 127 / 290, received one year later (T2–T5).
W5 Working capitalRequirement 250 / 260 / 270 / 281 → cash flows T0 (250), T1 (10), T2 (10), T3 (11), T4 +281 recovered.
$000T0T1T2T3T4T5
Revenue (W1)2,6003,2453,0932,632
Variable cost (W2)(1,260)(1,588)(1,528)(1,313)
Fixed cost (W3)(309)(318)(328)(338)
Taxable cash flow1,0311,3391,237982
Tax @ 30% (1 yr later)(309)(402)(371)(295)
CA tax benefit (W4)225169127290
Machine / scrap(3,000)300
Working capital (W5)(250)(10)(10)(11)281
Net cash flow(3,250)1,0211,2449941,318(5)
DF @ 11%1.0000.9010.8120.7310.6590.593
PV(3,250)9201,010727868(3)
NPV+272

Comment (2 marks): The NPV is positive at $272,000, so the project increases shareholder wealth and is financially acceptable. The margin is modest relative to a $3m outlay, so management should check the sensitivity of the key estimates (selling price, volume) before committing.

Examiner trapMarks lost by weak scripts on exactly this layout: fixed costs inflated at 4% instead of 3%; tax in the same year; no T5 column at all (loses the year-4 tax and the balancing allowance benefit); working capital as 250 every year instead of the increase; scrap forgotten in the CA computation; no comment.

Worked example: post-tax sensitivity and IRR

This continues from Ravi Co. These are the two calculations the examiner says candidates most often get wrong.

Ravi Co (continued)

Question

Using the NPV above, calculate the sensitivity of the project to (i) selling price and (ii) the discount rate. Comment. (6 marks)

Answer

(i) Selling price — a change in price changes revenue and the tax on revenue one year later, so the denominator is the PV of the post-tax revenue flows:

$000T1T2T3T4T5
Revenue2,6003,2453,0932,632
Tax @ 30% (1 yr later)(780)(974)(928)(790)
Net2,6002,4652,1191,704(790)
DF @ 11%0.9010.8120.7310.6590.593
PV2,3432,0021,5491,123(468)

PV of post-tax revenue = 6,549. Sensitivity = 272 ÷ 6,549 = 4.2%. A fall in selling price of just over 4% (with everything else unchanged) makes the NPV zero.

(ii) Discount rate — find the IRR. NPV at 11% = +272. Try 20%:

$000T0T1T2T3T4T5
Net cash flow(3,250)1,0211,2449941,318(5)
DF @ 20%1.0000.8330.6940.5790.4820.402
PV(3,250)851863575635(2)

NPV at 20% = (328). IRR ≈ 11% + [272 ÷ (272 + 328)] × (20% − 11%) = 11% + 4.1% = 15.1%.

Discount-rate sensitivity = (15.1% − 11%) ÷ 11% = 37%. The cost of capital would have to rise by 37% (from 11% to about 15%) before the project became unacceptable.

Comment (2 marks): The project is far more sensitive to selling price (4.2%) than to the discount rate (37%). Management should focus on the reliability of the price forecast and the inflation assumption behind it; a small competitive price cut would remove the whole NPV. Sensitivity analysis considers one variable at a time and does not give probabilities, so it indicates where risk lies rather than how likely it is.

Examiner trapThe three recurring errors: (1) dividing NPV by undiscounted or pre-tax revenue; (2) reporting "IRR − 11% = 4.1%" as the sensitivity instead of 4.1 ÷ 11 = 37%; (3) writing "the project is sensitive to price" without saying what the % means for the decision.
← PreviousWorking capitalNext →Finance and cost of capital

Frequently asked questions

How do I lay out an NPV in ACCA FM?

Put the years across the top and one line for each cash flow: revenue, variable costs, fixed costs, taxable cash flow, tax, capital allowance tax benefit, investment and scrap, working capital, net cash flow, discount factor and present value. Label every working and finish with the NPV and a decision.

What does tax payable one year in arrears mean for the NPV?

Every tax cash flow moves one column to the right. Tax on year 1 cash flows is paid in year 2, and a four-year project needs a year 5 column for the last tax payment and the last capital allowance benefit. Leaving out that column is one of the most common lost marks.

How is sensitivity calculated in FM?

Sensitivity of a variable = NPV ÷ present value of the cash flows relating to that variable, post-tax where tax applies. For the discount rate it is (IRR − cost of capital) ÷ cost of capital. The lowest percentage is the most sensitive variable.

Should I use the real or the nominal method?

Use the nominal method by default: inflate each cash flow at its own rate and discount at the nominal rate. The real method is valid only when every cash flow inflates at the general rate of inflation.

Start your ACCA preparation

Hamzah Academy teaches every ACCA paper from BT to AAA, with live online classes, every class recorded, and specialist tutors with a decade or more of experience.

1. Ask us anything

Message our team about papers, sittings and fees.

WhatsApp us
2. Try a free lesson

Watch our tutors teach before you pay.

YouTube
3. Enrol online

Pick your paper and pay by card on our website.

Free courses

Related pages

How to pass ACCA FMFM: working capitalFM: finance and cost of capitalACCA FM course
Hamzah Academy

Join Community

2000+ members

Hamzah Academy

150+ Videos

Instagram

350+ Posts

Important Links

Contact Us ACCA Global Office ACCA Exam/Key Dates Blog Privacy Policy Terms & Conditions Refund Policy

Sessions

December 2026
December 2026 March 2027

Contact Us

WhatsApp

+92 301 9191500

Call us

+92 301 9191500

Email

info@hamzah.academy

Facebook Page

18,000+ Followers

Study ACCA by Country

Azerbaijan · Bahrain · Bangladesh · Botswana · Cambodia · Canada · China · Cyprus · Egypt · Georgia · Ghana · Hong Kong · India · Indonesia · Ireland · Kazakhstan · Kenya · Kyrgyzstan · Luxembourg · Malaysia · Maldives · Malta · Mauritius · Moldova · Myanmar · Nepal · Nigeria · Oman · Pakistan · Poland · Rwanda · Saudi Arabia · Singapore · South Africa · Sri Lanka · Switzerland · Tanzania · Trinidad and Tobago · UAE · Uganda · UK · Uzbekistan · Vietnam · Zambia · Zimbabwe
© 2026 Hamzah Academy. All rights reserved.
Contact Foundation (FIA) WhatsApp Support