ACCA FM business valuation and risk management
One formula per valuation method plus why the answers differ, then foreign currency and interest rate risk: the quote direction and the money market hedge steps must be automatic.
Areas F and G of ACCA FM are mostly examined in Sections A and B, where each question is 2 marks with no partial credit. That makes method the whole game: the right side of the exchange rate quote, the discount on a proxy P/E, D1 and not D0. This guide follows Hamzah’s revision notes for both areas, with two worked examples and a Section B case.
Business valuations
Valuation methods
Debt & other securities
Why you value & why answers differ
Market efficiency & share prices
Under semi-strong EMH the quoted price is the best estimate of value — a bid at a premium implies expected synergies.
Practical influences on price: interest rates, market sentiment, sector news, dividend announcements, liquidity of the stock, speculation.
Fundamental analysis (intrinsic value from future cash flows) vs technical/chartist (past patterns) vs random walk (prices move randomly around fair value).
Typical Section B question set
Q1 net assets, Q2 P/E with discount, Q3 DVM with g = rb, Q4 bond price at a new yield, Q5 a statement question on EMH / reasons for the valuation range.
Worked example: valuing an unquoted company three ways
The dividend model with g = rb, the P/E method with a marketability discount, the asset basis, and then the range.
Sable Co (unquoted)
Question
5 million shares. Earnings $2.5m (EPS $0.50), dividend $1.5m (DPS $0.30) — payout 60%, so retention 40%. Return on reinvested funds 15%.
Net assets at realisable value $16m. Quoted competitors trade on a P/E of 12.
Risk-free rate 4%, equity risk premium 7%, appropriate equity beta 1.1.
Required: value one share on (i) dividend, (ii) P/E and (iii) net-asset bases, and explain the range. (10 marks)
Answer
(i) Dividend valuation model
g = r × b = 15% × 40% = 6%. Ke (CAPM) = 4% + 1.1 × 7% = 11.7%.
P0 = D0(1 + g) ÷ (Ke − g) = 0.30 × 1.06 ÷ (0.117 − 0.06) = 0.318 ÷ 0.057 = $5.58 per share ($27.9m).
(ii) P/E basis
Quoted P/E 12, discounted by one-third for lack of marketability → 8. Value = 0.50 × 8 = $4.00 per share ($20m).
(iii) Net assets: 16m ÷ 5m = $3.20 per share.
Explaining the range ($3.20 – $5.58)
Net assets is the floor — the minimum a seller should accept; it ignores goodwill, brand, workforce and earning power, so it is rarely the price for a going concern.
P/E values the earnings stream using the market's view of similar quoted companies; the discount is a judgement (⅓–½) reflecting that unquoted shares are illiquid and the company may be smaller/riskier than the proxies.
DVM is most relevant to a minority shareholder who only receives dividends; it relies on g continuing indefinitely (r and b constant) and on Ke from CAPM — small changes in Ke − g move the value a lot.
A majority buyer would prefer a cash-flow or earnings basis (control of the whole cash flow) and might add synergies; the actual price will be negotiated between the floor and the buyer's maximum.
Risk management: foreign currency and interest rates
500,000 ÷ 1.0125 = €493,827493,827 ÷ 1.1250 = $438,957438,957 × 1.0075 = $442,250500,000 ÷ (1 + 0.035 × 3/12) = €495,663495,663 ÷ 1.1200 = $442,556442,556 × 1.015 = $449,194Types of risk
Exchange rate theory
Internal hedging (free)
Invoice in home currency; matching receipts and payments (foreign-currency bank account); netting within a group; leading (paying early when the foreign currency is expected to strengthen) and lagging (delaying when it is expected to weaken); do nothing if small.
Money market hedge — the steps
External hedging instruments
Forward rate from interest rate parity
Worked example: money market hedge against a forward contract
A foreign currency receipt. This structure appears in Section A or B almost every sitting.
Lark Co (home currency $)
Question
Lark Co will receive €500,000 in three months.
Required: which hedge gives the higher dollar receipt? (5 marks)
Answer
Forward contract
Lark sells euros → the bank buys euros → the bank uses the rate that gives Lark fewer dollars, i.e. the higher € per $ figure: 500,000 ÷ 1.1210 = $446,030, received in three months.
Money market hedge — a receipt, so: borrow the foreign currency now, sell it at spot, deposit the home currency.
1. Euro loan today so that loan + interest = €500,000 in 3 months: 500,000 ÷ (1 + 0.05 × 3/12) = 500,000 ÷ 1.0125 = €493,827
2. Convert at spot (bank buys euros at 1.1250): 493,827 ÷ 1.1250 = $438,957
3. Place on dollar deposit for 3 months at 3% × 3/12 = 0.75%: 438,957 × 1.0075 = $442,250
4. In three months the €500,000 receipt repays the euro loan exactly.
Comparison: forward $446,030 vs MMH $442,250 → the forward contract gives about $3,780 more. Both give certainty; choose the forward.
Why the marks go where they do
Payment version — the mirror image
Paying €500,000 in 3 months, euro deposit 3.5%, dollar borrowing 6%: deposit €500,000 ÷ (1 + 0.035 × 3/12) = €495,663 now; buy those euros at spot 1.1200 (bank sells € — lower €/$ figure) = $442,556 borrowed today; repay 442,556 × (1 + 0.06 × 3/12) = $449,194 in three months. Compare with the forward cost 500,000 ÷ 1.1150 = $448,430.
Section B case drill: Pallas Co
Five independent 2-mark questions on a foreign currency payment. Allow 18 minutes.
Case 3 — Pallas Co (risk management, area G)
Pallas Co (home currency $) must pay €400,000 in six months.
Q1Dollar cost using a forward contract =
Q2Euro deposit required today for a money-market hedge =
Q3Dollar cost in six months using the money-market hedge =
Q4Which hedge should Pallas choose, and which risk is being hedged?
Q5The forward rate shows the euro at a premium to the dollar. This is consistent with:
Frequently asked questions
What are the steps in a money market hedge?
For a foreign currency receipt: borrow the foreign currency now, convert it at spot, and deposit the home currency; the receipt repays the loan. For a payment: deposit the foreign currency now, buying it at spot with borrowed home currency. Interest rates are annual, so pro-rate them for the period.
Which exchange rate do I use from a bid and offer quote?
The bank buys low and sells high, so you always get the worse rate. If you are selling foreign currency, use the rate that gives you less home currency; if you are buying it, use the rate that costs you more.
Why discount the P/E ratio when valuing an unquoted company?
A quoted company’s shares are easy to sell and the company is usually larger and less risky. Applying a quoted P/E to an unquoted company without a discount of roughly one-third to one-half overstates its value, and it is the classic lost mark.
What is the difference between transaction, translation and economic risk?
Transaction risk is an actual cash gain or loss on a foreign currency transaction between contract and settlement, and it is the one companies hedge. Translation risk is an accounting effect on consolidation with no cash flow. Economic risk is the long-term effect of exchange rates on competitiveness.
Start your ACCA preparation
Hamzah Academy teaches every ACCA paper from BT to AAA, with live online classes, every class recorded, and specialist tutors with a decade or more of experience.
Message our team about papers, sittings and fees.
WhatsApp usWatch our tutors teach before you pay.
YouTubePick your paper and pay by card on our website.
Free courses